Road Projects

______________________________________________________________________________

The Village of Little Chute Department of Public Works is constantly undertaking a variety of projects ranging form road construction, water and sewer replacement and storm water management. Throughout the course of the year, road project updates will be available.


Community Bridge Roadwork -
Maes Avenue in Kimberly to Wisconsin 96 in Little Chute


Outagamie County will begin concrete pavement repairs along County N between Maes Avenue and Wisconsin 96 as early as July 1st with expected completion in early August.

For more information click here.


2019 Utility & Street Reconstruc

io



Project Update, Friday, June 21st


2019 UTILITY & STREET CONSTUCTION – EVERGREEN DRIVE

Schedule: June 2019 to October 2019

Project Description:

The proposed project consists of reconstructing approximately 5,230 centerline feet of roadway along Evergreen Drive from French Road to Holland Road in the Village of Little Chute, Outagamie County, Wisconsin.  The reconstruction project includes the following: replacement of the existing roadway, removal of any trees within the right-of-way that will be in conflict with utility or paving operation, storm sewer utility installation, sanitary sewer manhole adjustments, water main lowering, future utility stub outs for storm sewer, water main and sanitary sewer, reconstructing all side road intersections to match point, installing concrete curb & gutter, installation of reinforced (doweled) concrete pavement, and associated driveway and lawn restoration work.  The proposed roadway will be converted from a rural to urban typical section and widened from its current width (approximately 23-feet) to be 38-feet from face of curb to face of curb.  The proposed widening will include two (2) 12-foot drive lanes and a 14-foot two-way left turn lane.  The proposed roadway will be contained within the current 66-foot right-of-way.

Updated Weekly Schedule (June 24th to June 28th)

Work is scheduled to continue with the installation of storm sewer and relocation of private utilities. Don Hietpas & Sons is working on the installation of 48” storm sewer near the intersection of Cherryvale Ave. & Evergreen Drive, work is scheduled to continue west toward French Road. Evergreen Drive is an active construction site. For your safety as well as those working in the area, please avoid use when possible.

Traffic Impacts: Evergreen Drive is closed to through traffic. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Residents, business owners, and customers may access properties past “ROAD CLOSED – LOCAL TRAFFIC ONLY” signs. Parking is not permitted on the street, access for drop off and pick up are allowed. Residents should expect additional restrictions due to installation of proposed utilities.

2019 ASPHALT PAVING PROJECTS - PARK AVENUE ASPHALT PAVING

Schedule: June 2019 to October 2019

Project Description:

The proposed project consists of asphalt paving approximately 7,200 square yards. The utilities under the pavement are in good condition and will not require replacement.  This project will include the removal of the existing asphalt and gravel base.  The subgrade will be reshaped and compacted.  Finally, a new gravel base and asphalt pavement will be installed.  Additional work will include rim adjustment of structures and replacement of damaged curb and gutter in spot locations.

Project Schedule

Work is scheduled to begin on Park Avenue beginning the week of July 8th.

_______________________________________________________________________________

Project Update Monday, June 10th

Project Walk-Thru Dates Have Been Set

West Evergreen Drive – Wednesday, June 12th
For more information click here.

Park Avenue – Wednesday, June 26th
For more information click here.

_______________________________________________________________________________

Bid Documents

To bid on the 2019 utility and street reconstruction projects click the link here and enter the following quest numbers:

Park Avenue Asphalt Paving (2019001)
Quest E-Bid  Doc # 6255729

Evergreen Drive Storm Sewer (2019002)
Quest E-Bid  Doc # 6255906

 Evergreen Drive Concrete Paving (2019003)
Quest E-Bid  Doc # 6255921

West Evergreen Drive

The utility (storm Sewer) and concrete street reconstruction is necessary on West Evergreen Drive to accommodate new development and increased traffic load.  The proposed work includes new concrete pavement with integral curb and gutter, storm sewer, and grass restoration areas. The new pavement on West Evergreen Drive will be comprised of two 12-foot-wide drive lanes and one 14-foot-wide common center turning lane. 

Park Avenue

Asphalt pavement replacement is needed on Park Avenue because it has reached the useful life expectancy of the pavement. Because the utilities are in relatively good condition with curb and gutter requiring only spot repairs it is best to replace the asphalt pavement and not install a 50-year concrete pavement over the ageing infrastructure.  With asphalt being approximately half the cost of concrete at approximately half the life cycle, it is economically more feasible to provide a pavement that will last 20 to 25 years to better match with the utilities life cycle before a total reconstruction is necessary. The existing condition of the asphalt pavement has reached a level where maintenance continues to increase without extending the pavement life.  A pavement overlay is not an option due to the current condition of the pavement and subbase.  To prevent further surface water intrusion and to correct sub-base rutting the pavement will be removed and subbase regraded and compacted prior to placement of granular base material and new asphalt pavement.

Public Informational Meeting – 4/3/19

Click here for meeting outline.

Public Hearing - 4/17/19

Click here for Frequently Asked Questions.

Click here for power point presentation.


WIS 441 Bridge Painting
Project Location:  WIS 441 over Fox River, WIS 96, and Railroad Outagamie County

WISDOT will be conducting a maintenance painting project on the WIS 441 bridge over the Fox River, WIS 96, and Canadian National Railroad. Anticipated work will begin in April 2018.  Work will continue until November 2018 and finish any remaining work in April of 2019.  

WIS 441 will remain open to at least one lane of traffic in each direction at all times during the project.  The single lane closures will be limited to nighttime only from 8:00 pm to 6:00 am.


Thank you for your patience throughout the reconstruction process!