Road Projects

______________________________________________________________________________

The Village of Little Chute Department of Public Works is constantly undertaking a variety of projects ranging form road construction, water and sewer replacement and storm water management. Throughout the course of the year, road project updates will be available.


Hickory Drive Closed - Starting Monday, September 21st Until Further Notice


The section of Hickory Drive from “N” / Freedom Road to Don DeGroot Drive will be closed for the Nestle Plant expansion to thru traffic.

If you have any questions call the Department of Public Works, (920) 423-3865. 

Road Closed – No Thru Traffic County “N” (Madison Street) & Pine Street

County “N” / Madison Street Detour – Starting Monday, September 21st to Thursday, October 1st

County “N” / Madison Street (From State Hwy 96 / Main Street to McKinley Avenue) will be closed starting Monday, September 21st for utility work for the Cobblestone Hotel & Suites.  See map.

The detour route will be as follows:  County “N” to County “OO” (North Avenue), East on County “OO” (North Avenue) to Rosehill Road, South on Rosehill Road to Hwy 96 (Main Street),  West on Highway 96 (Main Street).


Pine Street North of Church Street to Canal Street- Starting Monday, September 21st

The above section of Pine Street will be officially vacated to make room for St. John’s parking lot expansion.  See map.

If you have any questions call the Department of Public Works, (920) 423-3865. 


Moasis Drive Detour

On Monday; August 10th, 2020 the Village of Little Chute will begin reconstruction of the water main and replacement of effected concrete pavement.  Dorner Inc. was selected as the General Contractor and will be installing the new water main. Vinton Construction Co. will be the sub-contractor in charge of the concrete pavement replacement. During construction the Village is allowing Moasis Drive to be closed on a block by block basis for the safety of those trying to pass through the construction zone, as well as the crews working in a confined area.

The Contractor will be setting up a detour which will route truck traffic as follows:

South on Freedom Road (CTH “N”) to E. North Avenue (CTN “OO”)
East on E. North Avenue (CTN “OO”) to Buchanan Street
North on Buchanan Street to destination

For more information click here.

For map of detour click here.

Questions?
   Call (920) 423-3865.


2020 WATER MAIN REPLACEMENT – MOASIS DRIVE

Schedule: August 2020 to October 2020

Project Description:

The project entails reconstruction of approximately 2,670 centerline feet of local water mains and adjoining pavements along Moasis Drive from Freedom Road to Buchanan Road in the Village of Little Chute, Outagamie County, Wisconsin.

The existing water main infrastructure along the project has become ineffective and or deteriorated and is need of replacement.  The aged ductile-iron water main has experienced multiple breaks along the roadway.  Street work consists of excavation to subgrade and the installation of new stone base, concrete pavement, concrete curb and gutter, driveway approaches and landscaping.  

UPDATED WEEKLY SCHEDULE - (September 21st to September 25th)

MOASIS DRIVE UTILITIES

Dorner has begun the water main replacement beginning at Buchanan Street and continued west on Moasis Drive to Kelly Street. Dorner will be finishing construction of the water main and water services this week between Buchanan Street and Kelly Street. Miscellaneous storm sewer work is also being performed throughout the project as needed. Dorner will start installation of the water main between Freedom Road and Kelly Street next week Tuesday, September 22nd. Moasis Drive is an active construction site. For your safety as well as those working in the area, please avoid use when possible.   

MOASIS DRIVE PAVING

Vinton Construction Co. is the sub-contractor to Dorner Inc. on Moasis Drive for the concrete paving operations. Vinton anticipates using a paver for the concrete replacement upon completion of the utility work. Updates on the paving schedule will be communicated as that work is scheduled during the construction process.

Traffic Impacts: Moasis Drive is closed to ALL traffic. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Residents, business owners, and customers should work with the Contractor and coordinate access to properties past “ROAD CLOSED” signs, if necessary. Parking is not permitted on the street, access for drop off and pick up are allowed. Residents should expect additional restrictions due to installation of proposed utilities. Truck traffic is restricted to the posted detour which is as follows: Freedom Road - south to E. North Avenue (“N”), E. North Avenue - east to Buchanan Road, then north on Buchanan Rd. and vice versa.  Evergreen Drive north of Highway 41 is posted and should not be used as an alternate route for truck traffic.

Beginning on Monday - September 21st, Moasis Drive between Freedom Road and Kelly Street will be CLOSED TO ALL TRAFFIC. Dorner anticipates this road closure will be in place through Friday, September 25th. Please use the posted truck detour route to access Moasis Drive, the detour is directed south on Freedom Road, then east on C.T.H. “OO”, then north on Buchanan Street to Moasis Drive.


2020 UTILITY & STREET CONSTRUCTION – HOMEWOOD COURT

2020 UTILITY & STREET CONSTRUCTION – HOMEWOOD COURT

Schedule: May 2020 to October 2020

Project Description:

The project scope of work includes reconstruction of approximately 1,550 centerline feet of roadway along Homewood Court from West Florida Avenue to West Florida Avenue in the Village of Little Chute.

The existing water main and storm sewer infrastructure along the project has become ineffective and or deteriorated and is in need of replacement.  The aged ductile iron water main has experienced multiple water main breaks and will be replaced with new PVC water main.  The storm sewer pipe is currently undersized for the area and is in need of upsizing.  Existing pavement condition has reached the end of its practical service life and is also in need of replacement.  Street work consists of excavation to proposed subgrade and the installation of new stone base, concrete pavement, concrete curb and gutter, driveway approaches, sidewalks, terrace restoration, and permanent signage.  The proposed typical section of Homewood Court includes 7-inches of concrete, over 8-inches of granular base material.  The new pavement will comprise of two 11-foot wide drive lanes and one 6-foot wide parking lane.

UPDATED WEEKLY SCHEDULE - (September 21st to September 25th)

HOMEWOOD COURT UTILITIES

Don Hietpas & Sons has completed the water, sanitary, and storm sewer utilities on Homewood Court. Miscellaneous construction and adjustments may continue in conjunction with the grading and paving efforts as needed. Homewood Court is an active construction site. For your safety as well as those working in the area, please avoid use when possible.   

HOMEWOOD COURT PAVING

Vinton Construction is the general contractor for the Village paving contract on Homewood Court. Vinton has completed the excavation and grading, as well as the mainline concrete pavement. Additional crews will be on-site intermittently to complete tie-ins and hand pours in phases. Vinton is scheduled to begin removal of existing concrete sidewalk and aprons on Monday, 9-21-20. Martell Construction will begin construction of new sidewalk and aprons later this week, weather permitting. Updates on the paving schedule will be posted if changes are necessary.

Traffic Impacts: Homewood Court is closed to through traffic. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Residents, business owners, and customers may access properties past “ROAD CLOSED – LOCAL TRAFFIC ONLY” signs. Parking is not permitted on the street, access for drop off and pick up are allowed. Residents should expect additional restrictions due to installation of proposed utilities.

2020 UTILITY & STREET CONSTRUCTION – CAROL LYNN DRIVE

Schedule: June 2020 to October 2020

Project Description:

The project entails reconstruction of approximately 1,670 centerline feet of roadway along Carol Lynn Drive from East Lincoln Avenue to East Wisconsin Avenue in the Village of Little Chute.

The existing water main and storm sewer infrastructure along the project has become ineffective and or deteriorated and is need of replacement.  The ductile iron water main has experienced multiple water main breaks, new PVC water main will be installed.  The storm sewer is currently undersized for the area and is need of upsizing.  The current pavement has reached the end of its service life and is need of replacement.  Street work consists of excavation to subgrade and the installation of new stone base, concrete pavement, concrete curb and gutter, driveway approaches, sidewalks, terrace restoration, and permanent signage.  The proposed typical section of Carol Lynn Drive includes 7-inches of concrete, over 8-inches of granular base material.  The new pavement will comprise of two 11-foot wide drive lanes and one 6-foot wide parking lane.

UPDATED WEEKLY SCHEDULE - (September 21st to September 25th)

CAROL LYNN DRIVE UTILITIES

Don Hietpas & Sons has completed the water, sanitary, and storm sewer utilities on Carol Lynn Drive. Miscellaneous construction and adjustments may continue in conjunction with the grading and paving efforts as needed. Carol Lynn Drive is an active construction site. For your safety as well as those working in the area, please avoid use when possible.   

CAROL LYNN DRIVE PAVING

Vinton Construction is the general contractor for the Village paving contract on Carol Lynn Drive. Vinton has completed the excavation and grading, as well as the mainline concrete pavement. Additional crews will be on-site intermittently to complete the tie-ins and hand pours in phases. Vinton is scheduled to begin the removal of existing concrete sidewalk and aprons at the end of this week. Vinton will begin construction of new sidewalk and aprons after existing pavement removals are completed. Updates on the paving schedule will be posted as more information becomes available.

Traffic Impacts: Carol Lynn Drive is closed to through traffic. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Residents, business owners, and customers may access properties past “ROAD CLOSED – LOCAL TRAFFIC ONLY” signs. Parking is not permitted on the street, access for drop off and pick up are allowed. Residents should expect additional restrictions due to installation of proposed utilities.


2020 Village of Little Chute Projects

For a full description of each project click here.  Any questions regarding projects call (920) 423-3865.

              *Railroad Quiet Zones    *Moasis Drive *Vandenbroek Pond
                                             *Homewood Court              *Carol Lynn Drive

Updates:

Prior to the reconstruction of underground infrastructure and pavement on Homewood Ct, WE Energies and their subcontractor Michel’s Construction will start gas main relocation Monday, April 6, 2020. They will start on the west entrance of Homewood Ct and W. Florida Ave. It is anticipated that the main will take a week to install and gas up. At that time, they will transfer services from the old main on to the new main. All construction is planned to be completed by Friday April 24, 2020.


To bid on the 2020 utility and street reconstruction projects click the link here and enter the following quest numbers:

2020 Concrete Paving - Homewood Court and Carol Lynn Drive

Quest E-Bid  Doc # 6726167

2020 Utilities Project - Homewood Court and Carol Lynn Drive
Quest E-Bid  Doc # 6724625

2020 Railroad Quiet Zone Crossing Implementation
Quest E-Bid Doc # 6840686

2020 Water Main Reconstruction - Moasis Drive
Quest E-Bid Doc # 6840612


Bore Hole Testing

The Village will be conducting bore hole testing the week of February 3rd - 7th for our 2020 projects – Homewood Court, Carol Lynn Drive, Vandenbroek Pond and Moasis Drive. 

Bore hole testing is used to find out the structure and content of the ground / soil before construction begins.  If you have any questions call (920) 423-3865.


Public Hearing Carol Lynn Drive and Homewood Court:

           Date:                Wednesday, February 19, 2020
             Time:                6:00 p.m.
             Location:          Village Hall, Village Board Room

Click here for outline presented at Public Hearing Meeting.

Click here for frequently asked questions presented at Public Hearing Meeting.

Click here for the Preliminary Engineer's Report.


Public Informational Meeting Carol Lynn Drive and Homewood Court:

 Date:                Wednesday, January 8th, 2020
            Time:                6:00 p.m.
             Location:         Village Hall, Village Board Room

Click here for outline presented at Public Informational Meeting.

Public Informational Meeting Moasis Drive, Vandenbroek Pond, and Railroad Quiet Zones:

Date:                Wednesday, January 22, 2020
            Time:                6:00 p.m.
             Location:         Village Hall, Village Board Room

Click here for outline presented at Public Informational Meeting.


         Thank you for your patience throughout the reconstruction process!